Bagwan Complex, Peth Areas
by Shree Bhawani Builders. Peth Areas, Pune 411002. View on Google Maps
- Launched
- 4 years 4 months promised
- Possession date (MahaRERA)
- 1 year 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 0%Early stage
- Units booked
- Bookings not reported
Project facts
| 1 BHK | 8 |
|---|---|
| 2 BHK | 4 |
| Other units (shops, offices or not given by type) | 6 |
| Total units | 18 |
| Buildings | 1 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Compared with 5 similar projects in PIN 411002
Projects with up to 30 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs 4 mths | 3 yrs 6 mths |
| Possession date extended | No | 0 of 5 |
| Possession date (MahaRERA) | December 2027 | December 2026 |
| Concrete structure (RCC) complete | 0% | 35% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Anand | June 2023 | December 2026 | 35% | The 1 unit is booked |
| Sai Towers | June 2023 | December 2026 | 30% | Bookings not reported |
| Vitthal Niwas | November 2023 | December 2027 | 0% | Bookings not reported |
| Jai Proposed Building at CTS No. 1113/A, Subhash Nagar,Shukrawar Peth,Pune | December 2023 | December 2026 | 90% | 5 of 16 booked (31%) |
| Sadashiv Niwas | February 2023 | December 2026 | 100% | 18 of 36 booked (50%) |
Construction progress
As reported to MahaRERA at each updateWork not started as of Jul 2026
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Bagwan Complex (MahaRERA P52100052246) is a residential project by Shree Bhawani Builders in Peth Areas, Pune 411002. It was launched in August 2023. It has 18 units in 1 building: 12 homes (1 & 2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.
It has not reported any bookings to MahaRERA yet.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.