Golfland, Lavale

by Image Realty Private Limited. Lavale, Pune 412115. View on Google Maps

Launched
First of 4 phases
Possession dates (MahaRERA)
Dec 2028 – Dec 2029varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
16%Mid-construction0 of 4 phases with structure completeWeighted across 4 phases
Units booked
499 of 54392% booked

Project facts

1 BHK22
2 BHK130
3 BHK254
4 BHK88
Total units543
Buildings8
Land0.8 acres
Phases4
MahaRERA complaints (filed by or against the builder)0

Since Dec 2025: booked 408 → 499

Share on WhatsApp

Shortlist 2 or more to compare side by side.

The 4 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Golfland I and II
Mid-construction
P5210005237613128%93%
Golfland III and IV
Mid-construction
P5210005252213127%88%
Golfland VII and VIII
Early stage
P521000525301160%93%
Golfland V and VI
Mid-construction
P521000525311164%94%
Show updates by phase

Golfland I and II (P52100052376)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%28%0%122
100%8%0%111
100%0%0%112
100%0%0%61
0%0%0%26

"—" means MahaRERA shows no figure for that update.

Golfland III and IV (P52100052522)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%27%0%119
100%11%0%115
100%0%0%108
100%0%0%105
0%0%0%20

"—" means MahaRERA shows no figure for that update.

Golfland VII and VIII (P52100052530)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%128
100%0%0%83
28%0%0%73
0%0%0%50
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Golfland V and VI (P52100052531)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%4%0%130
100%0%0%99
100%0%0%57
0%0%0%43
0%0%0%—

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Golfland is a project by Image Realty Private Limited in Lavale, Pune 412115, registered with MahaRERA as 4 phases (P52100052376, P52100052522, P52100052530, P52100052531). The first phase was launched in August 2023. Together the phases have 543 units in 8 buildings, with 1, 2, 3 & 4 BHK homes as registered with MahaRERA. All 4 phases are active on MahaRERA.

The phases' registered possession dates run from December 2028 to December 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 16% complete and final finishes 0% complete. 0 of the 4 phases have their structure complete.

499 of the 543 units reported for sale are booked (92%).

Source: MahaRERA registrations P52100052376, P52100052522, P52100052530 and P52100052531.Open MahaRERA and search P52100052376All projects in Bhugaon, Bhukum, Pirangut, Lavale