Lotus Sheetal, Kothrud
by Lotus Landmarks. Kothrud, Pune 411038. View on Google Maps
- Launched
- 3 years 3 months promised
- Possession date (MahaRERA)
- 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 0%Early stage
- Units booked
- Bookings not reported
Project facts
| 2 BHK | 6 |
|---|---|
| 3 BHK | 6 |
| Other units (shops, offices or not given by type) | 9 |
| Total units | 21 |
| Buildings | 1 |
| Land | 0.4 acres |
| Landowner share | 8 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Compared with 6 similar projects in PIN 411038
Projects with up to 30 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 3 mths | 2 yrs 4 mths |
| Possession date extended | No | 3 of 6 |
| Possession date (MahaRERA) | December 2026 | January 2027 |
| Concrete structure (RCC) complete | 0% | 100% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Prathamesh Co-op Housing Soc | September 2023 | September 2026 | 100% | 12 of 17 booked (71%) |
| Grazia | September 2023 | June 2026 | 100% | 16 of 18 booked (89%) |
| TEJ Navya | September 2023 | December 2026 | 100% | 10 of 29 booked (34%) |
| Ravikeshar | August 2023 | December 2025 | 0% | 3 of 7 booked (43%) |
| Ved Anandghan | August 2023 | January 2027 | 100% | 12 of 21 booked (57%) |
| Suyog Laukik Apartment | July 2023 | December 2027 | 100% | 5 of 9 booked (56%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | — | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Lotus Sheetal (MahaRERA P52100052702) is a residential project by Lotus Landmarks in Kothrud, Pune 411038. It was launched in September 2023. It has 21 units in 1 building: 12 homes (2 & 3 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.
It has not reported any bookings to MahaRERA yet.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.