Joyville Celestia, Shewalewadi

by Joyville Shapoorji Housing Private Limited. Shewalewadi, Pune 412307. View on Google Maps

Launched
First of 5 phases
Possession dates (MahaRERA)
Mar 2028 – Sep 2029varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
26%Mid-construction0 of 5 phases with structure completeWeighted across 5 phases
Units booked
563 of 1,15849% booked

Project facts

2 BHK945
3 BHK207
4 BHK6
Total units1,158
Buildings7
Land1.1 acres
Phases5
MahaRERA complaints (filed by or against the builder)0
Share on WhatsApp

Shortlist 2 or more to compare side by side.

The 5 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Joyville Celestia Phase 2
Mid-construction
P5210005315915365%81%
Joyville Celestia Phase 1
Mid-construction
P5210005316516085%64%
Joyville Celestia Phase 3
Mid-construction
P521000555248440%76%
Joyville Celestia Phase 5
Mid-construction
P5210007694516920%61%
Joyville Celestia Phase 6
Early stage
P521000776425920%29%
Show updates by phase

Joyville Celestia Phase 2 (P52100053159)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%65%20%124
100%0%0%110
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Joyville Celestia Phase 1 (P52100053165)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%85%0%103
100%5%0%47
100%0%0%47
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Joyville Celestia Phase 3 (P52100055524)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%40%0%64
100%0%0%14

"—" means MahaRERA shows no figure for that update.

Joyville Celestia Phase 5 (P52100076945)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%20%0%103
100%0%0%—
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Joyville Celestia Phase 6 (P52100077642)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%169
0%0%0%—

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Joyville Celestia is a project by Joyville Shapoorji Housing Private Limited in Shewalewadi, Pune 412307, registered with MahaRERA as 5 phases (P52100053159, P52100053165, P52100055524, P52100076945, P52100077642). The first phase was launched in October 2023. Together the phases have 1,158 units in 7 buildings, with 2, 3 & 4 BHK homes as registered with MahaRERA. All 5 phases are active on MahaRERA.

The phases' registered possession dates run from March 2028 to September 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 26% complete and final finishes 3% complete. 0 of the 5 phases have their structure complete.

563 of the 1,158 units reported for sale are booked (49%).

Source: MahaRERA registrations P52100053159, P52100053165, P52100055524, P52100076945 and P52100077642.Open MahaRERA and search P52100053159All projects in Manjari, Shewalewadi