Ananta, Rahatani

by KK and Legacy Developers · Rahatani, Pune 411017 · Map

Launched
Oct 20231 yr 2 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 2 yrs
Concrete structure
100%Average of 4 towers
Booked
51 of 5789% · 32 in Jul 2026
Price per sq ft
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
36
Other units
21
Total units
57
Buildings
4
Land
0.6 acres
Phases
1
MahaRERA complaints
1

Construction progress

From the architect's Form 1 filed with MahaRERA, latest filing Sep 2026. The last 4 updates per tower.

How construction has progressed

Each point is a progress report the builder's architect filed with MahaRERA (Form 1). A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Oct 2024Feb 2025Jul 2026Sep 2026Oct 2024: Excavation 100%Feb 2025: Excavation 100%Jul 2026: Excavation 100%Sep 2026: Excavation 100%Oct 2024: Concrete structure (RCC) 87%Feb 2025: Concrete structure (RCC) 89%Jul 2026: Concrete structure (RCC) 89%Sep 2026: Concrete structure (RCC) 100%Oct 2024: Final finishes 1%Feb 2025: Final finishes 26%Jul 2026: Final finishes 26%Sep 2026: Final finishes 76%Excavation 100%Concrete structure (RCC) 100%Final finishes 76%
Last 4 updates, tower by tower
Building
UpdateStructureFinishes
Sep 2026100%100%
Jul 2026100%100%
Feb 2025100%100%
Oct 2024*96%50%
Building A
UpdateStructureFinishes
Sep 2026100%100%
Jul 202460%–
Apr 202450%–
Building B
UpdateStructureFinishes
Sep 2026100%100%
Jul 202696%–
Feb 202596%–
Jul 2024*100%50%
Building C
UpdateStructureFinishes
Sep 2026100%2%
Oct 2024100%3%
Apr 2024100%0%
Jan 2024100%0%

* Lower than the builder's previous filing for that tower.

Excavation is 100% in every tower.

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%76%51
100%100%75%32
100%100%75%32
100%100%75%32

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Construction cost spent

From the engineer's Form 2 filed with MahaRERA.

₹17.2 crore spent · latest estimate ₹17.2 crore · Sep 2026

Latest estimate ₹17.2 croreOct 2024: ₹14.9 crore14.9Oct 2024Feb 2025: ₹16.3 crore16.3Feb 2025Jul 2026: ₹16.3 crore16.3Jul 2026Sep 2026: ₹17.2 crore17.2Sep 2026
₹ crore spent
Spent at each update
UpdateSpent
Sep 2026₹17.2 crore
Jul 2026₹16.3 crore
Feb 2025₹16.3 crore
Oct 2024₹14.9 crore

About this project

Ananta by KK and Legacy Developers is a 57-unit project in Rahatani, Pune 411017, launched in October 2023 with possession due in December 2026. 51 units booked out of total 57 units. The concrete structure (RCC) is complete.

Read full summary

Ananta is a project by KK and Legacy Developers in Rahatani, Pune 411017, registered with MahaRERA as P52100053184. It was launched in October 2023. It has 57 units in 4 buildings: 36 homes (3 BHK) and 21 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 2 years from the original December 2024. Construction, averaged across its 4 towers: excavation complete, structure (RCC) complete, final finishes 76% complete.

51 units booked out of total 57 units (89%). Since the July 2026 update, 19 more units have been booked and the possession date has moved from December 2024 to December 2026.