Skip to main content
← Back

One Aretha Phase 1, Dhanori

by Triaa Landmarks LLP. Dhanori, Pune 411015. View on Google Maps

Launched
4 years 11 months promised
Possession date (MahaRERA)
2 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
9%Mid-constructionAverage across 4 buildings
Units booked
209 of 35060% booked

Project facts

1 BHK10
2 BHK93
3 BHK207
4 BHK16
Other units (shops, offices or not given by type)24
Total units350
Buildings4
Land2.8 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 91 → 209

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years 9 months of the promised 4 years 11 months have passed
Concrete structure (RCC) 9% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Jun 2024: Excavation 10%Dec 2024: Excavation 27%Jun 2025: Excavation 27%Dec 2025: Excavation 24%Jul 2026: Excavation 24%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 7%Jun 2025: Concrete structure (RCC) 7%Dec 2025: Concrete structure (RCC) 9%Jul 2026: Concrete structure (RCC) 9%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 24%Concrete structure (RCC) 9%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
24%9%0%209
24%9%0%91
27%7%0%106
10%0%0%56

"—" means MahaRERA shows no figure for that update.

About this project

One Aretha Phase 1 (MahaRERA P52100054352) is a residential project by Triaa Landmarks LLP in Dhanori, Pune 411015. It was launched in January 2024. It has 350 units in 4 buildings: 326 homes (1, 2, 3 & 4 BHK) and 24 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction, averaged across its 4 buildings: excavation 24% complete, structure (RCC) 9% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

209 of its 350 units are booked (60%). Since the December 2025 update, 118 more units have been booked.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100054352.Check it on MahaRERA (P52100054352)All projects in Dhanori, Dighi, Vishrantwadi