Skip to main content
← Back

Bramhacorp Townhouse A, Balewadi

by Bramhacorp Limited. Balewadi, Pune 411045. View on Google Maps

Launched
3 years 11 months promised
Possession date (MahaRERA)
1 year 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Nearing possession
Units booked
27 of 4068% booked

Project facts

1 RK25
Other units (shops, offices or not given by type)15
Total units40
Buildings1
Land0.7 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 16 → 27 · structure 98% → 100%

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years 9 months of the promised 3 years 11 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 98%Jul 2026: Concrete structure (RCC) 100%Jun 2024: Final finishes 0%Dec 2024: Final finishes 28%Jun 2025: Final finishes 28%Dec 2025: Final finishes 28%Jul 2026: Final finishes 28%Excavation 100%Concrete structure (RCC) 100%Final finishes 28%

If a percentage drops between updates, we show it as MahaRERA reported it.

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%28%27
100%98%28%16
100%100%28%4
100%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Bramhacorp Townhouse A (MahaRERA P52100054406) is a residential project by Bramhacorp Limited in Balewadi, Pune 411045. It was launched in January 2024. It has 40 units in 1 building: 25 homes (1 RK) and 15 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 28% complete. MahaRERA records do not show it as ready to move in.

27 of its 40 units are booked (68%). Since the December 2025 update, 11 more units have been booked and the reported concrete structure (RCC) has gone from 98% to 100%.

Bramhacorp's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA15
Completed without extending the possession date4
Completed after an extension, or lapsed0
Under construction11
Possession date extended by the builder0
Typical time from launch to 100% structure3 years 2 months
Complaints on MahaRERA, all Bramhacorp projects3 (3 of 15 projects)

See all Bramhacorp projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100054406.Check it on MahaRERA (P52100054406)All projects in Baner, Balewadi, Mahalunge