- Launched
- Feb 20242 yrs 2 mths originally promised
- Possession (MahaRERA)
- Feb 2027Extended by 10 mths
- Concrete structure
- 100%Ready to move
- Booked
- 33 of 3594% · 4 in Jul 2026
- Price per sq ft
- ₹7,0002026 sales · up 4% on 2025
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
What buyers paid
Registered sales, not today's asking price.
| Type | Size, sq ft | Most paid | Year |
|---|---|---|---|
| 2 BHK | 660 | ₹44–45 lakh | 2025 |
| 2 BHK | 760 | ₹48–49 lakh | 2025 |
Price per sq ft, year by year
| Year | Price per sq ft | On previous year |
|---|---|---|
| 2026 | ₹7,000 | ↑ 4% |
| 2025 | ₹6,700 | – |
About 35% below the typical Tathawade rate in 2026.
How to read this price
- Price per sq ft is the typical rate in that year's registered sales.
- Size is total internal area: carpet + balcony + terrace.
- Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
- The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
- Use it as a starting point for questions, not as an offer price.
Project facts
- 2 BHK
- 28
- Other units
- 7
- Total units
- 35
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress by tower
From the architect's Form 1 filed with MahaRERA. The last 4 updates per tower.
How construction has progressed
Each point is a progress report the builder's architect filed with MahaRERA (Form 1). A line that stays flat means no new progress was reported between two dates.
Last 4 updates
| Update | Structure | Finishes |
|---|---|---|
| Aug 2026 | 100% | 90% |
| May 2026 | 100% | 90% |
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 33 | |
| 100% | 0% | 0% | 4 | |
| 100% | 0% | 0% | 4 | |
| 100% | 0% | 0% | 4 |
"–" means MahaRERA shows no figure for that update.
Construction cost spent
From the engineer's Form 2 filed with MahaRERA.
₹5.4 crore spent · latest estimate ₹5.5 crore · Aug 2026
The builder raised the estimate from ₹5.2 crore to ₹5.5 crore in Aug 2026.
Spent at each update
| Update | Spent |
|---|---|
| Aug 2026 | ₹5.4 crore |
| Jun 2025 | ₹1.5 crore |
| Feb 2025 | ₹1.2 crore |
| Apr 2024 | ₹34 lakh |
Compared with 6 similar projects in PIN 411033
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 2 mths | 2 yrs 4 mths |
| Possession date extended | By 10 mths | 3 of 6 |
| Possession date (MahaRERA) | Feb 2027 | Dec 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked | 94% | 48% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects, latest price per sq ft
- Snehal Apartment, Chinchwad
- Yojana Heritage, Chinchwad
- Abhishek Sahakari Gruhrachana Sanstha Maryadit, Chinchwad
- Shantais Divine Vastu, Punawale
- The Enclave 1, Tathawade
- Soham Srushti, Tathawade₹8,400 · 2025
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Snehal Apartment | February 2024 | June 2026 | 100% | 15 units booked out of total 28 units |
| Yojana Heritage | February 2024 | September 2026 | 100% | 20 units booked out of total 20 units |
| Abhishek Sahakari Gruhrachana Sanstha Maryadit | February 2024 | December 2026 | 100% | 38 units booked out of total 38 units |
| Shantais Divine Vastu | January 2024 | December 2026 | 100% | 15 units booked out of total 73 units |
| The Enclave 1 | January 2024 | December 2030 | 100% | 15 units booked out of total 42 units |
| Soham Srushti | March 2024 | December 2026 | 100% | 24 units booked out of total 56 units |
About this project
Audumbar Green A Wing by Alankar Bagal Group is a 35-unit project in Tathawade, Pune 411033, launched in February 2024 with possession due in February 2027. 33 units booked out of total 35 units. Typical rate: ₹7,000 per sq ft (2026 registered sales).
Read full summary
Audumbar Green A Wing is a project by Alankar Bagal Group in Tathawade, Pune 411033, registered with MahaRERA as P52100054752. It was launched in February 2024. It has 35 units in 1 building: 28 homes (2 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is February 2027, extended by 10 months from the original April 2026. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
33 units booked out of total 35 units (94%). Since the July 2026 update, 29 more units have been booked, the reported concrete structure (RCC) has gone from 0% to 100% and the possession date has moved from April 2026 to February 2027. In 2026 registered sales, the typical rate here was ₹7,000 per sq ft (up 4% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 35% lower than the typical Tathawade rate in 2026. Most buyers paid ₹44–45 lakh for 2 BHK flats of about 660 sq ft (2025 sales); ₹48–49 lakh for 2 BHK flats of about 760 sq ft (2025 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.