East World, Manjari Budruk

by Sankla-Mahadik Realty. Manjari Budruk, Pune 412307. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Dec 2027 – Dec 2028varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
75%Mid-construction0 of 2 phases with structure completeWeighted across 2 phases
Units booked
171 of 23573% booked
Price per sq ft
₹9,0002026 salesup 2% on 2025See what buyers paid

Project facts

1 BHK6
2 BHK140
3 BHK94
Total units240
Buildings4
Land1.3 acres
Phases2
MahaRERA complaints (filed by or against the builder)0

Since Dec 2025: booked 153 → 171

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
1 RK / 1 BHKabout 510 – 530 sq ft₹42 – 44 lakh2025 sales
2 BHKabout 700 – 860 sq ft₹57 – 69 lakh2026 sales
3 BHKabout 990 sq ft₹77 – 86 lakh2026 sales

Price per sq ft, year by year

2024₹8,300 per sq ft
2025up 6% on 2024₹8,800 per sq ft
2026up 2% on 2025₹9,000 per sq ft

Registered sales across all 2 phases.

Compared with the typical Manjari Budruk rate in 2026: about 5% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
East World Phase - I
Mid-construction
P5210005477418475%66%
East World Phase - II
Mid-construction
P521000775165675%88%
Show updates by phase

East World Phase - I (P52100054774)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%75%30%122
100%45%0%108
100%0%0%—
30%0%0%—

"—" means MahaRERA shows no figure for that update.

East World Phase - II (P52100077516)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%75%20%49
100%70%0%45
100%0%0%31

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

East World is a project by Sankla-Mahadik Realty in Manjari Budruk, Pune 412307, registered with MahaRERA as 2 phases (P52100054774, P52100077516). The first phase was launched in February 2024. Together the phases have 240 units in 4 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. All 2 phases are active on MahaRERA.

The phases' registered possession dates run from December 2027 to December 2028; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 75% complete and final finishes 28% complete. 0 of the 2 phases have their structure complete.

171 of the 235 units reported for sale are booked (73%). In 2026 registered sales, 80% of flats here sold at ₹9,000 per sq ft or less (up 2% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 5% lower than the typical Manjari Budruk rate in 2026. Most buyers paid ₹42–44 lakh for 1 RK / 1 BHK flats of about 510–530 sq ft (2025 sales); ₹57–69 lakh for 2 BHK flats of about 700–860 sq ft (2026 sales); ₹77–86 lakh for 3 BHK flats of about 990 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100054774 and P52100077516.Open MahaRERA and search P52100054774All projects in Manjari, Shewalewadi