Skip to main content
← Back

Maitree Mega City, Dhayari

by Maitree Infra. Dhayari, Pune 411041. View on Google Maps

Launched
3 years 10 months promised
Possession date (MahaRERA)
1 year 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
8%Mid-constructionAverage across 3 buildings
Units booked
137 of 31244% booked

Project facts

1 RK1
1 BHK206
2 BHK95
Other units (shops, offices or not given by type)10
Total units312
Buildings3
Land2.8 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 127 → 137 · final finishes 30% → 33%

Share on WhatsApp

Compared with 3 similar projects in PIN 411041

Projects with 150–700 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 411041
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 10 mths4 yrs 2 mths
Possession date extendedNo1 of 3
Possession date (MahaRERA)December 2027December 2027
Concrete structure (RCC) complete8%50%
Share of units booked44%16%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years 8 months of the promised 3 years 10 months have passed
Concrete structure (RCC) 8% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Jun 2024: Excavation 50%Dec 2024: Excavation 50%Jun 2025: Excavation 50%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Jun 2024: Concrete structure (RCC) 3%Dec 2024: Concrete structure (RCC) 5%Jun 2025: Concrete structure (RCC) 5%Dec 2025: Concrete structure (RCC) 8%Jul 2026: Concrete structure (RCC) 8%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 30%Jul 2026: Final finishes 33%Excavation 100%Final finishes 33%Concrete structure (RCC) 8%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%8%33%137
100%8%30%127
50%5%0%71
50%3%0%35

"—" means MahaRERA shows no figure for that update.

About this project

Maitree Mega City (MahaRERA P52100055000) is a residential project by Maitree Infra in Dhayari, Pune 411041. It was launched in February 2024. It has 312 units in 3 buildings: 302 homes (1 RK, 1 BHK & 2 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) 8% complete, final finishes 33% complete. MahaRERA records do not show it as ready to move in.

137 of its 312 units are booked (44%). Since the December 2025 update, 10 more units have been booked.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100055000.Check it on MahaRERA (P52100055000)All projects in Dhayari