Skip to main content
← Back

Suparshwanath E Co-op. Housing Society Ltd., Market Yard

by Rahul Lifespaces LLP. Market Yard, Pune 411037. View on Google Maps

Launched
3 years 6 months promised
Possession date (MahaRERA)
11 months awayPossession date unchanged since launch
Concrete structure (RCC)
50%Mid-construction
Units booked
11 of 1368% booked

Project facts

3 BHK6
4 BHK108
Other units (shops, offices or not given by type)22
Total units136
Buildings1
Land1.8 acres
Landowner share2
Rehab units76
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 9 → 11 · total units 126 → 136

Share on WhatsApp

Compared with 3 similar projects in PIN 411037

Projects with 50–250 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 411037
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 6 mths4 yrs 8 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)September 2027June 2028
Concrete structure (RCC) complete50%20%
Share of units booked8%35%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years 7 months of the promised 3 years 6 months have passed
Concrete structure (RCC) 50% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 18%Jun 2025: Concrete structure (RCC) 18%Dec 2025: Concrete structure (RCC) 50%Jul 2026: Concrete structure (RCC) 50%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 50%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%50%0%11
100%50%0%9
100%18%0%—
100%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Suparshwanath E Co-op. Housing Society Ltd. (MahaRERA P52100055173) is a residential project by Rahul Lifespaces LLP in Market Yard, Pune 411037. It was launched in March 2024. It has 136 units in 1 building: 114 homes (3 & 4 BHK) and 22 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is September 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 50% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

11 of its 136 units are booked (8%). Since the December 2025 update, 2 more units have been booked.

Rahul Construction's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA10
Completed without extending the possession date4
Completed after an extension, or lapsed3
Under construction3
Possession date extended by the builder3
Typical time from launch to 100% structure2 years 2 months
Complaints on MahaRERA, all Rahul Construction projects10 (5 of 10 projects)

See all Rahul Construction projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100055173.Check it on MahaRERA (P52100055173)All projects in Gultekdi, Bibwewadi