IRA Icon, Dighi
Finishing stage
Final finishes 100% · completion not yet filed on MahaRERA
by Tirupati Associates. Dighi, Pune 411031. View on Google Maps
- Launched
- 2 years 6 months promised
- Possession date (MahaRERA)
- 1 month agoPossession date unchanged since launch
- Concrete structure (RCC)
- 100%Finishing stage
- Units booked
- 8 of 2829% booked
Project facts
| 1 BHK | 14 |
|---|---|
| 2 BHK | 14 |
| Total units | 28 |
| Buildings | 1 |
| Land | 0.1 acres |
| Landowner share | 9 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 7 → 8 · final finishes 0% → 100%
Compared with 3 similar projects in PIN 411031
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 2 yrs 6 mths | 2 yrs 8 mths |
| Possession date extended | No | 2 of 3 |
| Possession date (MahaRERA) | September 2026 | April 2027 |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 29% | 50% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| S. No. 1A/1,2,3,1B - Aarambha Residency | February 2024 | December 2027 | 70% | 12 of 36 booked (33%) |
| Golden Core | October 2023 | June 2026 | 100% | 8 of 16 booked (50%) |
| Sunway | October 2023 | August 2026 | 100% | 9 of 16 booked (56%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 8 | |
| 100% | 100% | 0% | 7 | |
| 100% | 40% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
IRA Icon (MahaRERA P52100055253) is a residential project by Tirupati Associates in Dighi, Pune 411031. It was launched in March 2024. It has 28 units in 1 building, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is September 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.
8 of its 28 units are booked (29%). Since the December 2025 update, 1 more unit has been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.