Raj Kunj, Kiwale
Finishing stage
Final finishes 96% · completion not yet filed on MahaRERA
by Swaraj Kundalik Amale. Kiwale, Pune 412101. View on Google Maps
- Launched
- 2 years 8 months promised
- Possession date (MahaRERA)
- 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 100%Finishing stage
- Units booked
- 27 of 5549% booked
Project facts
| 1 BHK | 20 |
|---|---|
| 2 BHK | 35 |
| Total units | 55 |
| Buildings | 1 |
| Land | 0.3 acres |
| Landowner share | 14 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 25 → 27 · final finishes 0% → 96%
Compared with 5 similar projects in PIN 412101
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 2 yrs 8 mths | 4 yrs 5 mths |
| Possession date extended | No | 0 of 5 |
| Possession date (MahaRERA) | December 2026 | June 2028 |
| Concrete structure (RCC) complete | 100% | 30% |
| Share of units booked | 49% | 13% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sky Stories | May 2024 | March 2029 | 30% | 4 of 58 booked (7%) |
| Samarth Serenity Building C | June 2024 | October 2026 | 40% | 24 of 54 booked (44%) |
| Opulent Tower | July 2024 | June 2027 | 100% | 7 of 54 booked (13%) |
| Little Earth, Kiwale - Building C14 | January 2024 | June 2028 | 11% | Bookings not reported |
| Little Earth, Kiwale - Building C13 | January 2024 | June 2028 | 13% | Bookings not reported |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 96% | 27 | |
| 100% | 100% | 0% | 25 | |
| 100% | 63% | 0% | 12 | |
| 100% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Raj Kunj (MahaRERA P52100055724) is a residential project by Swaraj Kundalik Amale in Kiwale, Pune 412101. It was launched in April 2024. It has 55 units in 1 building, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 96% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
27 of its 55 units are booked (49%). Since the December 2025 update, 2 more units have been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.