Belmont Skyverse, Lohegaon
Finishing stage
Final finishes 90% · completion not yet filed on MahaRERA
by Belmont Realty. Lohegaon, Pune 411047. View on Google Maps
- Launched
- 4 years 4 months promised
- Possession date (MahaRERA)
- 1 year 10 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 100%Finishing stageAverage across 2 buildings
- Units booked
- 127 of 14190% booked
Project facts
| 2 BHK | 114 |
|---|---|
| 3 BHK | 13 |
| 4 BHK | 14 |
| Total units | 141 |
| Buildings | 2 |
| Land | 0.9 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 106 → 127 · structure 85% → 100% · final finishes 60% → 90%
Compared with 4 similar projects in PIN 411047
Projects with 70–300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs 4 mths | 3 yrs |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | August 2028 | March 2027 |
| Concrete structure (RCC) complete | 100% | 90% |
| Share of units booked | 90% | 58% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| VNSVL Shubh Nirvana Phase III | March 2024 | December 2026 | 100% | 96 of 132 booked (73%) |
| VNSVL Shubh Nirvana Phase IV | March 2024 | June 2027 | 0% | 28 of 136 booked (21%) |
| Nivasa Ananya Phase I | June 2024 | December 2026 | 86% | 144 of 196 booked (73%) |
| Mindspace Residency Phase - 1 | July 2024 | December 2027 | 95% | 104 of 245 booked (42%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 127 | |
| 100% | 85% | 60% | 106 | |
| 100% | 0% | 0% | 14 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Belmont Skyverse (MahaRERA P52100055743) is a residential project by Belmont Realty in Lohegaon, Pune 411047. It was launched in April 2024. It has 141 units in 2 buildings, with 2, 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is August 2028, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
127 of its 141 units are booked (90%). Since the December 2025 update, 21 more units have been booked and the reported concrete structure (RCC) has gone from 85% to 100%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.