Ravikiran Annexe Phase II, Wadmukhwadi
by Dreamhouse Constructions Private Limited. Wadmukhwadi, Pune 412105. View on Google Maps
- Launched
- 3 years 10 months promised
- Possession date (MahaRERA)
- 1 year 4 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 100%Nearing possessionAverage across 3 buildings
- Units booked
- 157 of 18485% booked
Project facts
| 1 BHK | 88 |
|---|---|
| 2 BHK | 86 |
| Other units (shops, offices or not given by type) | 10 |
| Total units | 184 |
| Buildings | 3 |
| Land | 2.4 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 91 → 157 · final finishes 33% → 79%
Compared with 6 similar projects in PIN 412105
Projects with 80–350 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 10 mths | 4 yrs |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | February 2028 | December 2028 |
| Concrete structure (RCC) complete | 100% | 54% |
| Share of units booked | 85% | 68% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Kumar Parv F, G AND H | April 2024 | December 2028 | 7% | 114 of 240 booked (48%) |
| PRK Miracle | April 2024 | December 2026 | 100% | 72 of 110 booked (65%) |
| Kumar Parv A, B, C, D AND E | May 2024 | December 2031 | 7% | 55 of 240 booked (23%) |
| Sankalp Alyssum | March 2024 | June 2026 | 100% | 138 of 147 booked (94%) |
| Kamalraj Akshardham B and C Building | May 2024 | December 2028 | 100% | 168 of 220 booked (76%) |
| Vision 24DEGREE | June 2024 | December 2027 | 0% | 231 of 322 booked (72%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 79% | 157 | |
| 100% | 100% | 33% | 91 | |
| 100% | 63% | 0% | 12 | |
| 67% | 2% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Ravikiran Annexe Phase II (MahaRERA P52100055879) is a residential project by Dreamhouse Constructions Private Limited in Wadmukhwadi, Pune 412105. It was launched in April 2024. It has 184 units in 3 buildings: 174 homes (1 & 2 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is February 2028, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) complete, final finishes 79% complete. MahaRERA records do not show it as ready to move in.
157 of its 184 units are booked (85%). Since the December 2025 update, 66 more units have been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.