Skip to main content
← Back

Empire Square Phase III, Chinchwad

by Empire Properties. Chinchwad, Pune 411019. View on Google Maps

Launched
6 years 7 months promised
Possession date (MahaRERA)
4 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
50%Mid-construction
Units booked
139 of 35239% booked

Project facts

2 BHK166
3 BHK103
4 BHK71
Other units (shops, offices or not given by type)12
Total units352
Buildings1
Land10.3 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 35 → 139 · structure 5% → 50% · total units 212 → 352

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years 5 months of the promised 6 years 7 months have passed
Concrete structure (RCC) 50% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 5%Jun 2025: Concrete structure (RCC) 5%Dec 2025: Concrete structure (RCC) 5%Jul 2026: Concrete structure (RCC) 50%Jun 2024: Final finishes 50%Dec 2024: Final finishes 50%Jun 2025: Final finishes 50%Dec 2025: Final finishes 50%Jul 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 50%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%50%50%139
100%5%50%35
100%5%50%16
100%0%50%6

"—" means MahaRERA shows no figure for that update.

About this project

Empire Square Phase III (MahaRERA P52100056031) is a residential project by Empire Properties in Chinchwad, Pune 411019. It was launched in May 2024. It has 352 units in 1 building: 340 homes (2, 3 & 4 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2030, unchanged since launch. Construction: excavation complete, structure (RCC) 50% complete, final finishes 50% complete. MahaRERA records do not show it as ready to move in.

139 of its 352 units are booked (39%). Since the December 2025 update, 104 more units have been booked and the reported concrete structure (RCC) has gone from 5% to 50%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100056031.Check it on MahaRERA (P52100056031)All projects in Chinchwad MIDC