NB Skies, Ravet
by East West Developers. Ravet, Pune 412101. View on Google Maps
- Launched
- 3 years 1 month promised
- Possession date (MahaRERA)
- 8 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 0%Early stage
- Units booked
- 2 of 1811% booked
Project facts
| 3 BHK | 13 |
|---|---|
| 4 BHK | 5 |
| Total units | 18 |
| Buildings | 1 |
| Land | 0.5 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Compared with 6 similar projects in PIN 412101
Projects with up to 40 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 1 mth | 2 yrs 11 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | June 2027 | May 2027 |
| Concrete structure (RCC) complete | 0% | 65% |
| Share of units booked | 11% | 32% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Kesar Kalhaar | May 2024 | October 2026 | 100% | Bookings not reported |
| Sky Stories | May 2024 | March 2029 | 30% | 4 of 58 booked (7%) |
| Inspira | June 2024 | April 2027 | 0% | 7 of 18 booked (39%) |
| K K Marks B Building | June 2024 | June 2027 | 100% | 17 of 37 booked (46%) |
| Shivratna | March 2024 | July 2026 | 100% | 6 of 24 booked (25%) |
| Rajveer Park | August 2024 | December 2027 | 0% | Bookings not reported |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 2 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
NB Skies (MahaRERA P52100056112) is a residential project by East West Developers in Ravet, Pune 412101. It was launched in May 2024. It has 18 units in 1 building, with 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.
2 of its 18 units are booked (11%).
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.