Solitaire Kothrud, Kothrud
by Built to Live Realty Development NO 1 LLP. Kothrud, Pune 411038. View on Google Maps
- Launched
- First of 2 phases
- Possession dates (MahaRERA)
- Jun 2029 – Dec 2029varies by phaseNo phase has an extended possession date
- Concrete structure (RCC)
- 0%Early stage0 of 2 phases with structure completeWeighted across 2 phases
- Units booked
- 81 of 32625% booked
- Price per sq ft
- ₹17,9002026 salesup 4% on 2025See what buyers paid
Facts
Project facts
| 2 BHK | 3 |
|---|---|
| 3 BHK | 217 |
| 4 BHK | 88 |
| Total units | 326 |
| Buildings | 2 |
| Land | 1.1 acres |
| Phases | 2 |
Since Dec 2025: booked 71 → 81
Shortlist 2 or more to compare side by side.
Prices
What buyers paid here
From government sale recordsWhat buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.
Flat types, sizes and prices
| Flat type | Size (total internal area) | What most buyers paid | Year |
|---|---|---|---|
| 3 BHK | about 1,170 – 1,310 sq ft | ₹2.01 – 2.39 crore | 2026 sales |
| 4 BHK | about 1,840 sq ft | ₹2.85 – 3.33 crore | 2026 sales |
Price per sq ft, year by year
| 2024 | ₹17,000 per sq ft |
|---|---|
| 2025up 1% on 2024 | ₹17,200 per sq ft |
| 2026up 4% on 2025 | ₹17,900 per sq ft |
Registered sales across all 2 phases.
Compared with the typical Kothrud rate in 2026: similar
How to read this price
- 80% of registered sales that year were at this rate or less.
- Size is total internal area: carpet + balcony + terrace.
- Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
- The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
- Fewer sales means a less certain figure.
- Use it as a starting point for questions, not as an offer price.
Phases
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Solitaire Kothrud A Building Early stage | P52100056306 | 132 | 0% | 29% | |
| Solitaire Kothrud B Building Early stage | P52100056309 | 176 | 0% | 21% |
Show updates by phase
Solitaire Kothrud A Building (P52100056306)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 41 | |
| 100% | 0% | 0% | 34 | |
| 0% | 0% | 0% | 3 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Solitaire Kothrud B Building (P52100056309)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 40 | |
| 93% | 0% | 0% | 37 | |
| 0% | 0% | 0% | 16 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Compare
Compared with 4 similar projects in PIN 411038
Projects with 150–700 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 5 yrs 4 mths | 4 yrs 5 mths |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | Jun 2029 – Dec 2029 | December 2028 |
| Concrete structure (RCC) | 0% | 6% |
| Units booked | 25% | 34% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Mayuk | May 2024 | March 2031 | 13% | 89 of 277 booked (32%) |
| New Friends | April 2024 | December 2029 | 0% | 179 of 773 booked (23%) |
| Pushkar Park | October 2024 | December 2027 | 0% | Bookings not reported |
| Hillview Residency | November 2023 | Dec 2026 – Jun 2027 | 100% | 128 of 152 booked (84%) |
How to read construction stages
- Early stage
- The concrete structure (RCC) has not started yet.
- Mid-construction
- The concrete structure (RCC) is being built.
- Nearing possession
- The concrete structure (RCC) is complete and final finishes are below 90%.
- Ready to move
- MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
- Concrete structure (RCC)
- The reinforced-concrete frame of the building: columns, beams and slabs.
- Final finishes
- Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- Lapsed
- MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.
About this project
Solitaire Kothrud is a project by Built to Live Realty Development NO 1 LLP in Kothrud, Pune 411038, registered with MahaRERA as 2 phases (P52100056306, P52100056309). The first phase was launched in May 2024. Together the phases have 326 units in 2 buildings, with 2, 3 & 4 BHK homes as registered with MahaRERA. All 2 phases are active on MahaRERA.
The phases' registered possession dates run from June 2029 to December 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 0% complete and final finishes 0% complete. 0 of the 2 phases have their structure complete.
81 of the 326 units reported for sale are booked (25%). In 2026 registered sales, 80% of flats here sold at ₹17,900 per sq ft or less (up 4% on 2025), counting balconies and terrace in the size. Buyers here paid a rate similar to the typical Kothrud rate in 2026. Most buyers paid ₹2.01–2.39 crore for 3 BHK flats of about 1,170–1,310 sq ft (2026 sales); ₹2.85–3.33 crore for 4 BHK flats of about 1,840 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.