Awadh Nagari, Borhadewadi
by Chopra Kakde Realty LLP. Borhadewadi, Pune 412105. View on Google Maps
- Launched
- 3 years 6 months promised
- Possession date (MahaRERA)
- 1 year 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 50%Mid-constructionAverage across 2 buildings
- Units booked
- 113 of 30837% booked
Project facts
| 2 BHK | 172 |
|---|---|
| 3 BHK | 135 |
| Other units (shops, offices or not given by type) | 1 |
| Total units | 308 |
| Buildings | 2 |
| Land | 4 acres |
| Landowner share | 101 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 85 → 113 · structure 0% → 50%
Compared with 6 similar projects in PIN 412105
Projects with 150–700 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 6 mths | 4 yrs 5 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | December 2027 | December 2028 |
| Concrete structure (RCC) complete | 50% | 4% |
| Share of units booked | 37% | 74% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Vision 24DEGREE | June 2024 | December 2027 | 0% | 231 of 322 booked (72%) |
| Montreal - E-H | July 2024 | December 2028 | 0% | 184 of 224 booked (82%) |
| Kamalraj Akshardham B and C Building | May 2024 | December 2028 | 100% | 168 of 220 booked (76%) |
| Kesar Highstreet C Bldg | July 2024 | December 2027 | 0% | 107 of 217 booked (49%) |
| Kumar Parv A, B, C, D AND E | May 2024 | December 2031 | 7% | 55 of 240 booked (23%) |
| Silver Galaxy Phase II | July 2024 | December 2028 | 80% | 192 of 238 booked (81%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 50% | 0% | 113 | |
| 100% | 0% | 0% | 85 | |
| 100% | 0% | 0% | 12 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Awadh Nagari (MahaRERA P52100056464) is a residential project by Chopra Kakde Realty LLP in Borhadewadi, Pune 412105. It was launched in June 2024. It has 308 units in 2 buildings: 307 homes (2 & 3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) 50% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
113 of its 308 units are booked (37%). Since the December 2025 update, 28 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 50%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.