Suyog Rachana, Kothrud
by Suyog Development Corporation Pune LLP. Kothrud, Pune 411038. View on Google Maps
- Launched
- 2 years 8 months promised
- Possession date (MahaRERA)
- 5 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 10%Mid-construction
- Units booked
- Bookings not reported
Project facts
| 2 BHK | 29 |
|---|---|
| 3 BHK | 11 |
| 4 BHK | 1 |
| Total units | 41 |
| Buildings | 1 |
| Land | 0.2 acres |
| Landowner share | 1 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: structure 0% → 10%
Compared with 5 similar projects in PIN 411038
Projects with 20–90 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 2 yrs 8 mths | 2 yrs 11 mths |
| Possession date extended | No | 0 of 5 |
| Possession date (MahaRERA) | March 2027 | May 2027 |
| Concrete structure (RCC) complete | 10% | 50% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Pashupati | July 2024 | January 2027 | 100% | 6 of 33 booked (18%) |
| Soumitra | June 2024 | December 2028 | 50% | 10 of 44 booked (23%) |
| Ekam | August 2024 | May 2029 | 50% | 37 of 55 booked (67%) |
| Rajhans | June 2024 | May 2027 | 100% | 2 of 28 booked (7%) |
| Avika Trinity | August 2024 | December 2026 | 0% | Bookings not reported |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 10% | 0% | — | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Suyog Rachana (MahaRERA P52100076962) is a residential project by Suyog Development Corporation Pune LLP in Kothrud, Pune 411038. It was launched in July 2024. It has 41 units in 1 building, with 2, 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 10% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
It has not reported any bookings to MahaRERA yet. Since the December 2025 update, the reported concrete structure (RCC) has gone from 0% to 10%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.