Shyamalprabha, Kothrud
by Badhekar Developers. Kothrud, Pune 411038. View on Google Maps
- Launched
- 3 years 4 months promised
- Possession date (MahaRERA)
- 1 year 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 60%Mid-construction
- Units booked
- 1 of 147% booked
Project facts
| 1 BHK | 1 |
|---|---|
| 2 BHK | 12 |
| 3 BHK | 1 |
| Total units | 14 |
| Buildings | 1 |
| Land | 0.1 acres |
| Rehab units | 8 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: structure 80% → 60%
Compared with 6 similar projects in PIN 411038
Projects with up to 30 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 4 mths | 2 yrs 11 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | December 2027 | July 2027 |
| Concrete structure (RCC) complete | 60% | 85% |
| Share of units booked | 7% | 35% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Pradnyesh | August 2024 | December 2027 | 0% | Bookings not reported |
| Avika Trinity | August 2024 | December 2026 | 0% | Bookings not reported |
| Shrinivas Apartment | July 2024 | October 2026 | 90% | 5 of 12 booked (42%) |
| Vighnahar | July 2024 | January 2027 | 100% | 7 of 22 booked (32%) |
| Chandraat | July 2024 | March 2028 | 80% | 7 of 20 booked (35%) |
| Deepa | October 2024 | June 2029 | 100% | Bookings not reported |
Construction progress
As reported to MahaRERA at each updateIf a percentage drops between updates, we show it as MahaRERA reported it.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 60% | 0% | 1 | |
| 100% | 80% | 0% | — | |
| 90% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Shyamalprabha (MahaRERA P52100077390) is a residential project by Badhekar Developers in Kothrud, Pune 411038. It was launched in August 2024. It has 14 units in 1 building, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 60% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
1 of its 14 units is booked (7%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 80% to 60%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.