Skip to main content
← Back

5 RaceCourse By Skyi Phase II, Wanowrie

by Enerrgia Skyi Landmarks. Wanowrie, Pune 411040. View on Google Maps

Launched
3 years 8 months promised
Possession date (MahaRERA)
1 year 6 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stage
Units booked
Bookings not reported

Project facts

3 BHK27
4 BHK65
Other units (shops, offices or not given by type)32
Total units124
Buildings1
Land4.4 acres
Complaints on MahaRERA (filed by or against the builder)2
Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years 2 months of the promised 3 years 8 months have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Jun 2025Dec 2025Jul 2026Dec 2024: Excavation 0%Jun 2025: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%—
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

5 RaceCourse By Skyi Phase II (MahaRERA P52100077439) is a residential project by Enerrgia Skyi Landmarks in Wanowrie, Pune 411040. It was launched in August 2024. It has 124 units in 1 building: 92 homes (3 & 4 BHK) and 32 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2028, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

It has not reported any bookings to MahaRERA yet.

Skyi's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA41
Completed without extending the possession date17
Completed after an extension, or lapsed7
Under construction17
Possession date extended by the builder7
Typical time from launch to 100% structure3 years 4 months
Complaints on MahaRERA, all Skyi projects52 (20 of 41 projects)

See all Skyi projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100077439.Check it on MahaRERA (P52100077439)All projects in Wanawadi, Fatimanagar