Kalpataru Blossoms, Wadgaon Budruk

by Kalpataru Limited. Wadgaon Budruk, Pune 411041. View on Google Maps

Launched
First of 3 phases
Possession dates (MahaRERA)
Mar 2029No phase has an extended possession date
Concrete structure (RCC)
27%Mid-construction0 of 3 phases with structure completeWeighted across 3 phases
Units booked
174 of 47037% booked

Project facts

1 BHK4
2 BHK112
3 BHK277
4 BHK40
5+ BHK30
Total units470
Buildings6
Land3.3 acres
Phases3
MahaRERA complaints (filed by or against the builder)0

Since Dec 2025: booked 118 → 174

Share on WhatsApp

Shortlist 2 or more to compare side by side.

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Kalpataru Blossoms - Tower 2
Mid-construction
P5210007764921339%40%
Kalpataru Blossoms - Tower 1
Mid-construction
P521000776597041%19%
Kalpataru Blossoms - Tower 3
Mid-construction
P521000777501808%41%
Show updates by phase

Kalpataru Blossoms - Tower 2 (P52100077649)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
98%39%0%85
0%0%0%55
0%0%0%33

"—" means MahaRERA shows no figure for that update.

Kalpataru Blossoms - Tower 1 (P52100077659)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
98%41%0%13
90%0%0%5
0%0%0%13

"—" means MahaRERA shows no figure for that update.

Kalpataru Blossoms - Tower 3 (P52100077750)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
92%8%0%76
0%0%0%58
0%0%0%70

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

Other phases of this project

About this project

Kalpataru Blossoms is a project by Kalpataru Limited in Wadgaon Budruk, Pune 411041, registered with MahaRERA as 3 phases (P52100077649, P52100077659, P52100077750). The first phase was launched in October 2024. Together the phases have 470 units in 6 buildings, with 1, 2, 3, 4 & 5+ BHK homes as registered with MahaRERA. All 3 phases are active on MahaRERA.

The registered possession date is March 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 27% complete and final finishes 0% complete. 0 of the 3 phases have their structure complete.

174 of the 470 units reported for sale are booked (37%).

Source: MahaRERA registrations P52100077649, P52100077659 and P52100077750.Open MahaRERA and search P52100077649All projects in Dhayari