Palaash Aarambh, Varale

by G.S Properties. Varale, Pune 410507. View on Google Maps

Launched
3 years 10 months promised
Possession date (MahaRERA)
1 year 10 months awayPossession date unchanged since launch
Concrete structure (RCC)
18%Mid-constructionAverage across 5 buildings
Units booked
6 of 1354% booked

Project facts

1 BHK56
Other units (shops, offices or not given by type)79
Total units135
Buildings5
Land4 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: structure 36% → 18% · total units 82 → 135

Share on WhatsApp

Compared with 3 similar projects in PIN 410507

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 410507
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 10 mths2 yrs 11 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)August 2028February 2028
Concrete structure (RCC) complete18%60%
Share of units booked4%24%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years of the promised 3 years 10 months have passed
Concrete structure (RCC) 18% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Jun 2025Dec 2025Jul 2026Dec 2024: Excavation 0%Jun 2025: Excavation 0%Dec 2025: Excavation 67%Jul 2026: Excavation 80%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 36%Jul 2026: Concrete structure (RCC) 18%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 80%Concrete structure (RCC) 18%Final finishes 0%

If a percentage drops between updates, we show it as MahaRERA reported it.

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
80%18%0%6
67%36%0%6
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Palaash Aarambh (MahaRERA P52100077754) is a residential project by G.S Properties in Varale, Pune 410507. It was launched in October 2024. It has 135 units in 5 buildings: 56 homes (1 BHK) and 79 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is August 2028, unchanged since launch. Construction, averaged across its 5 buildings: excavation 80% complete, structure (RCC) 18% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

6 of its 135 units are booked (4%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 36% to 18%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100077754.Check it on MahaRERA (P52100077754)All projects in Talegaon Dabhade, Darumbare