Swojas Emerald, Erandwane
by Swojas Estate PVT Ltd. Erandwane, Pune 411004. View on Google Maps
- Launched
- 2 years 4 months promised
- Possession date (MahaRERA)
- 5 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 45%Mid-construction
- Units booked
- 13 of 4827% booked
Project facts
| 1 RK | 14 |
|---|---|
| 1 BHK | 1 |
| 2 BHK | 10 |
| 3 BHK | 17 |
| Other units (shops, offices or not given by type) | 6 |
| Total units | 48 |
| Buildings | 1 |
| Land | 0.2 acres |
| Landowner share | 12 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 10 → 13 · structure 10% → 45%
Compared with 6 similar projects in PIN 411004
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 2 yrs 4 mths | 2 yrs 11 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | March 2027 | October 2027 |
| Concrete structure (RCC) complete | 45% | 25% |
| Share of units booked | 27% | 14% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Kamalapark Co-op Hsg. Society | November 2024 | August 2027 | 0% | 2 of 25 booked (8%) |
| VB Sapphire | November 2024 | September 2027 | 50% | 2 of 37 booked (5%) |
| Soujanya Sahakari Griha Rachana Sanstha Maryadit | November 2024 | January 2027 | 0% | 8 of 18 booked (44%) |
| Saraswati Niwas | November 2024 | November 2027 | 100% | 2 of 14 booked (14%) |
| Snehabhavan Cooperative Housing Society Limited | October 2024 | March 2028 | 0% | 3 of 16 booked (19%) |
| Yashodhan Co-operative Housing Society | October 2024 | March 2028 | 60% | 8 of 56 booked (14%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 45% | 0% | 13 | |
| 100% | 10% | 0% | 10 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Swojas Emerald (MahaRERA P52100077931) is a residential project by Swojas Estate PVT Ltd in Erandwane, Pune 411004. It was launched in November 2024. It has 48 units in 1 building: 42 homes (1 RK, 1 BHK, 2 BHK & 3 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 45% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
13 of its 48 units are booked (27%). Since the December 2025 update, 3 more units have been booked and the reported concrete structure (RCC) has gone from 10% to 45%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.