Skip to main content
← Back

Unitas TownHomes Wing A, Kondhwa Khurd

by Tingre Bizcorp Private Limited. Kondhwa Khurd, Pune 411048. View on Google Maps

Launched
7 years 2 months promised
Possession date (MahaRERA)
5 years 3 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stageAverage across 2 buildings
Units booked
19 of 12216% booked

Project facts

1 BHK48
2 BHK18
4 BHK4
Other units (shops, offices or not given by type)52
Total units122
Buildings2
Land0.6 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Compared with 6 similar projects in PIN 411048

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411048
MeasureThis projectSimilar projects
Promised timeline (launch to possession)7 yrs 2 mths4 yrs 2 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)January 2032December 2028
Concrete structure (RCC) complete0%20%
Share of units booked16%26%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 11 months of the promised 7 years 2 months have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Jun 2025Dec 2025Jul 2026Dec 2024: Excavation 0%Jun 2025: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 35%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 35%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
35%0%0%19
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Unitas TownHomes Wing A (MahaRERA P52100078108) is a residential project by Tingre Bizcorp Private Limited in Kondhwa Khurd, Pune 411048. It was launched in November 2024. It has 122 units in 2 buildings: 70 homes (1, 2 & 4 BHK) and 52 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is January 2032, unchanged since launch. Construction, averaged across its 2 buildings: excavation 35% complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

19 of its 122 units are booked (16%).

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100078108.Check it on MahaRERA (P52100078108)All projects in Kondhwa, Yewalewadi, Pisoli