Aarambh, Lavale
by Yogesh Dagdu Gaikwad. Lavale, Pune 412115. View on Google Maps
- Launched
- 3 years 10 months promised
- Possession date (MahaRERA)
- 1 year 11 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 0%Early stageAverage across 2 buildings
- Units booked
- Bookings not reported
Project facts
| 1 BHK | 12 |
|---|---|
| 2 BHK | 4 |
| Other units (shops, offices or not given by type) | 6 |
| Total units | 22 |
| Buildings | 2 |
| Land | 0.4 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Compared with 3 similar projects in PIN 412115
Projects with up to 40 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 10 mths | 4 yrs 11 mths |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | September 2028 | March 2029 |
| Concrete structure (RCC) complete | 0% | 0% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Serenora Wing A | June 2024 | December 2027 | 0% | 1 of 35 booked (3%) |
| Skyi Park Phase II | May 2025 | July 2030 | 0% | 9 of 18 booked (50%) |
| The Orchard Residences | April 2024 | March 2029 | 0% | 8 of 12 booked (67%) |
Construction progress
As reported to MahaRERA at each updateWork not started as of Jul 2026
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Aarambh (MahaRERA P52100078245) is a residential project by Yogesh Dagdu Gaikwad in Lavale, Pune 412115. It was launched in November 2024. It has 22 units in 2 buildings: 16 homes (1 & 2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is September 2028, unchanged since launch. Construction, averaged across its 2 buildings: excavation not started, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.
It has not reported any bookings to MahaRERA yet.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.