Skip to main content
← Back

RKH Nidhivan, Chikhali

by Mauli RKH Associates. Chikhali, Pune 412114. View on Google Maps

Launched
3 years promised
Possession date (MahaRERA)
1 year 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stageAverage across 3 buildings
Units booked
5 of 915% booked

Project facts

1 BHK22
2 BHK23
Other units (shops, offices or not given by type)46
Total units91
Buildings3
Land0.6 acres
Landowner share25
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 4 → 5

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 10 months of the promised 3 years have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Jun 2025Dec 2025Jul 2026Dec 2024: Excavation 0%Jun 2025: Excavation 0%Dec 2025: Excavation 33%Jul 2026: Excavation 33%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 33%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
33%0%0%5
33%0%0%4
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

RKH Nidhivan (MahaRERA P52100078364) is a residential project by Mauli RKH Associates in Chikhali, Pune 412114. It was launched in December 2024. It has 91 units in 3 buildings: 45 homes (1 & 2 BHK) and 46 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction, averaged across its 3 buildings: excavation 33% complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

5 of its 91 units are booked (5%). Since the December 2025 update, 1 more unit has been booked.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100078364.Check it on MahaRERA (P52100078364)All projects in Chikhali, Talwade