Arun Sanctum, Ravet
by Adev Ventures PVT Ltd. Ravet, Pune 412101. View on Google Maps
- Launched
- 6 years promised
- Possession date (MahaRERA)
- 4 years 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 0%Early stageAverage across 5 buildings
- Units booked
- 51 of 20625% booked
Project facts
| 2 BHK | 152 |
|---|---|
| 3 BHK | 52 |
| Other units (shops, offices or not given by type) | 2 |
| Total units | 206 |
| Buildings | 5 |
| Land | 2.7 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 25 → 51 · total units 144 → 206
Compared with 6 similar projects in PIN 412101
Projects with 100–450 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 6 yrs | 4 yrs 5 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | December 2030 | June 2029 |
| Concrete structure (RCC) complete | 0% | 4% |
| Share of units booked | 25% | 30% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Gini Vivante Phase 03 | December 2024 | December 2028 | 15% | 157 of 334 booked (47%) |
| Little Earth, Kiwale - Building D1 | January 2025 | June 2029 | 0% | 81 of 170 booked (48%) |
| Santiago Skytown | November 2024 | June 2027 | 0% | 118 of 163 booked (72%) |
| Little Earth, Kiwale - Buildng D2 | January 2025 | June 2029 | 1% | 9 of 149 booked (6%) |
| Maheshwaram Vrinda PHASE-1 | January 2025 | December 2030 | 8% | 6 of 143 booked (4%) |
| Yashada Dreamsong | November 2024 | December 2029 | 7% | 42 of 314 booked (13%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 20% | 0% | 0% | 51 | |
| 20% | 0% | 0% | 25 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Arun Sanctum (MahaRERA P52100078503) is a residential project by Adev Ventures PVT Ltd in Ravet, Pune 412101. It was launched in December 2024. It has 206 units in 5 buildings: 204 homes (2 & 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2030, unchanged since launch. Construction, averaged across its 5 buildings: excavation 20% complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.
51 of its 206 units are booked (25%). Since the December 2025 update, 26 more units have been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.