Skip to main content
← Back

Sai Nagari Phase IV, Gujar Nimbalkarwadi

by Saikedareshwar Developers LLP. Gujar Nimbalkarwadi, Pune 411046. View on Google Maps

Launched
5 years promised
Possession date (MahaRERA)
3 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stageAverage across 2 buildings
Units booked
259 of 45757% booked

Project facts

1 BHK457
Total units457
Buildings2
Land15.2 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 10 months of the promised 5 years have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Jun 2025Dec 2025Jul 2026Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%259
100%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Sai Nagari Phase IV (MahaRERA P52100078517) is a residential project by Saikedareshwar Developers LLP in Gujar Nimbalkarwadi, Pune 411046. It was launched in December 2024. It has 457 units in 2 buildings, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

259 of its 457 units are booked (57%).

Sai Nagari's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA5
Completed without extending the possession date0
Completed after an extension, or lapsed0
Under construction5
Possession date extended by the builder0
Complaints on MahaRERA, all Sai Nagari projects0 (0 of 5 projects)

See all Sai Nagari projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100078517.Check it on MahaRERA (P52100078517)All projects in Ambegaon, Katraj