Eastern River Residency Wing B, Pimple Gurav
by M/s Vinayak Enterprises. Pimple Gurav, Pune 411061. View on Google Maps
- Launched
- 4 years 11 months promised
- Possession date (MahaRERA)
- 3 years 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 18%Mid-construction
- Units booked
- 65 of 13150% booked
Project facts
| 3 BHK | 72 |
|---|---|
| Other units (shops, offices or not given by type) | 59 |
| Total units | 131 |
| Buildings | 1 |
| Land | 0.9 acres |
| Complaints on MahaRERA (filed by or against the builder) | 1 |
Since Dec 2025: booked 6 → 65 · structure 0% → 18%
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 18% | 0% | 65 | |
| 100% | 0% | 0% | 6 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Eastern River Residency Wing B (MahaRERA P52100078700) is a residential project by M/s Vinayak Enterprises in Pimple Gurav, Pune 411061. It was launched in January 2025. It has 131 units in 1 building: 72 homes (3 BHK) and 59 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 18% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
65 of its 131 units are booked (50%). Since the December 2025 update, 59 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 18%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.