Shakai, Tathawade
by Krisala Homes. Tathawade, Pune 411033. View on Google Maps
- Launched
- 3 years 9 months promised
- Possession date (MahaRERA)
- 2 years 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 2%Mid-constructionAverage across 2 buildings
- Units booked
- 588 of 67088% booked
Project facts
| 1 RK | 507 |
|---|---|
| 1 BHK | 36 |
| Other units (shops, offices or not given by type) | 127 |
| Total units | 670 |
| Buildings | 2 |
| Land | 2.3 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 328 → 588 · structure 0% → 2%
Compared with 6 similar projects in PIN 411033
Projects with 10–80 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 9 mths | 2 yrs 10 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | December 2028 | April 2028 |
| Concrete structure (RCC) complete | 2% | 0% |
| Share of units booked | 88% | 29% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Paradigam Vandan | March 2025 | February 2028 | 0% | 5 of 35 booked (14%) |
| Shashwat | March 2025 | December 2027 | 0% | 8 of 28 booked (29%) |
| Udyam Nagari | March 2025 | December 2029 | 0% | 21 of 60 booked (35%) |
| Prayagraj | March 2025 | December 2027 | 0% | Bookings not reported |
| Gurudeo | April 2025 | June 2028 | 100% | 5 of 22 booked (23%) |
| 24Life Altaa | January 2025 | October 2028 | 30% | 19 of 47 booked (40%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 50% | 2% | 0% | 588 | |
| 0% | 0% | 0% | 328 | |
| 0% | 0% | 0% | 124 |
"—" means MahaRERA shows no figure for that update.
About this project
Shakai (MahaRERA P52100079401) is a residential project by Krisala Homes in Tathawade, Pune 411033. It was launched in March 2025. It has 670 units in 2 buildings: 543 homes (1 RK & 1 BHK) and 127 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2028, unchanged since launch. Construction, averaged across its 2 buildings: excavation 50% complete, structure (RCC) 2% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
588 of its 670 units are booked (88%). Since the December 2025 update, 260 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 2%.
Krisala's track record in Pune
MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers
| Projects registered with MahaRERA | 32 |
|---|---|
| Completed without extending the possession date | 13 |
| Completed after an extension, or lapsed | 4 |
| Under construction | 15 |
| Possession date extended by the builder | 4 |
| Typical time from launch to 100% structure | 3 years 8 months |
| Complaints on MahaRERA, all Krisala projects | 99 (12 of 32 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not extend its possession date. MahaRERA's COVID extensions (6 + 6 months, 2020–21) are not counted as the builder's.
- Completed after an extension, or lapsed: every other registration that is not under construction.
- Under construction: MahaRERA status Active.
- Possession date extended by the builder: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure reached 100% between December 2023 and July 2026, counted from registration.
- Complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.