Skip to main content
← Back

Belmont Skydale, Lohegaon

by Belmont Realty. Lohegaon, Pune 411032. View on Google Maps

Launched
3 years 5 months promised
Possession date (MahaRERA)
1 year 10 months awayPossession date unchanged since launch
Concrete structure (RCC)
90%Mid-construction
Units booked
21 of 4250% booked

Project facts

3 BHK42
Total units42
Buildings1
Land0.9 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 9 → 21 · structure 15% → 90% · final finishes 0% → 40%

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 7 months of the promised 3 years 5 months have passed
Concrete structure (RCC) 90% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2025Dec 2025Jul 2026Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 15%Jul 2026: Concrete structure (RCC) 90%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 40%Excavation 100%Concrete structure (RCC) 90%Final finishes 40%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%40%21
100%15%0%9
100%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Belmont Skydale (MahaRERA P52100079413) is a residential project by Belmont Realty in Lohegaon, Pune 411032. It was launched in March 2025. It has 42 units in 1 building, with 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is August 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 90% complete, final finishes 40% complete. MahaRERA records do not show it as ready to move in.

21 of its 42 units are booked (50%). Since the December 2025 update, 12 more units have been booked and the reported concrete structure (RCC) has gone from 15% to 90%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100079413.Check it on MahaRERA (P52100079413)All projects in Pune Airport