Renuka Madhuban, Akurdi
by Anil Babu Mhetre. Akurdi, Pune 411035. View on Google Maps
- Launched
- 3 years 9 months promised
- Possession date (MahaRERA)
- 2 years 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 20%Mid-constructionAverage across 4 buildings
- Units booked
- 8 of 978% booked
Project facts
| 1 BHK | 1 |
|---|---|
| 2 BHK | 77 |
| 3 BHK | 11 |
| 4 BHK | 2 |
| Other units (shops, offices or not given by type) | 6 |
| Total units | 97 |
| Buildings | 4 |
| Land | 0.7 acres |
| Landowner share | 41 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 1 → 8 · structure 60% → 20%
Construction progress
As reported to MahaRERA at each updateIf a percentage drops between updates, we show it as MahaRERA reported it.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 25% | 20% | 0% | 8 | |
| 80% | 60% | 0% | 1 | |
| 60% | 15% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Renuka Madhuban (MahaRERA P52100079444) is a residential project by Anil Babu Mhetre in Akurdi, Pune 411035. It was launched in March 2025. It has 97 units in 4 buildings: 91 homes (1, 2, 3 & 4 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2028, unchanged since launch. Construction, averaged across its 4 buildings: excavation 25% complete, structure (RCC) 20% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
8 of its 97 units are booked (8%). Since the December 2025 update, 7 more units have been booked and the reported concrete structure (RCC) has gone from 60% to 20%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.