Skip to main content
← Back

Swapnpurti, Talegaon Dabhade

by A Square Buildcon. Talegaon Dabhade, Pune 410507. View on Google Maps

Launched
2 years promised
Possession date (MahaRERA)
5 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Nearing possession
Units booked
7 of 4615% booked

Project facts

1 BHK3
2 BHK20
3 BHK5
Other units (shops, offices or not given by type)18
Total units46
Buildings1
Land0.2 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 8 → 7 · structure 80% → 100% · final finishes 0% → 40%

Share on WhatsApp

Compared with 5 similar projects in PIN 410507

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 410507
MeasureThis projectSimilar projects
Promised timeline (launch to possession)2 yrs1 yr 8 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)March 2027September 2027
Concrete structure (RCC) complete100%95%
Share of units booked15%43%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 7 months of the promised 2 years have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2025Dec 2025Jul 2026Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 100%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 40%Excavation 100%Concrete structure (RCC) 100%Final finishes 40%

If a percentage drops between updates, we show it as MahaRERA reported it.

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%40%7
100%80%0%8
100%100%0%7

"—" means MahaRERA shows no figure for that update.

About this project

Swapnpurti (MahaRERA P52100079491) is a residential project by A Square Buildcon in Talegaon Dabhade, Pune 410507. It was launched in March 2025. It has 46 units in 1 building: 28 homes (1, 2 & 3 BHK) and 18 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 40% complete. MahaRERA records do not show it as ready to move in.

7 of its 46 units are booked (15%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 80% to 100%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100079491.Check it on MahaRERA (P52100079491)All projects in Talegaon Dabhade, Darumbare