Skip to main content
← Back

Vivanta Aaranya, Ravet

by Punamiya Urban Development LLP. Ravet, Pune 412101. View on Google Maps

Launched
1 year 9 months promised
Possession date (MahaRERA)
2 months awayPossession date unchanged since launch
Concrete structure (RCC)
75%Mid-constructionAverage across 18 buildings
Units booked
14 of 1878% booked

Project facts

Other units (shops, offices or not given by type)18
Total units18
Buildings18
Land0.9 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 6 → 14 · structure 36% → 75%

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 7 months of the promised 1 year 9 months have passed
Concrete structure (RCC) 75% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2025Dec 2025Jul 2026Jun 2025: Excavation 0%Dec 2025: Excavation 54%Jul 2026: Excavation 100%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 36%Jul 2026: Concrete structure (RCC) 75%Jun 2025: Final finishes 0%Dec 2025: Final finishes 4%Jul 2026: Final finishes 4%Excavation 100%Concrete structure (RCC) 75%Final finishes 4%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%75%4%14
54%36%4%6
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Vivanta Aaranya (MahaRERA P52100079508) is a residential project by Punamiya Urban Development LLP in Ravet, Pune 412101. It was launched in March 2025. It has 18 units, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction, averaged across its 18 buildings: excavation complete, structure (RCC) 75% complete, final finishes 4% complete. MahaRERA records do not show it as ready to move in.

14 of its 18 units are booked (78%). Since the December 2025 update, 8 more units have been booked and the reported concrete structure (RCC) has gone from 36% to 75%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100079508.Check it on MahaRERA (P52100079508)All projects in Kiwale, Ravet