Shangrila Heights, Bavdhan Khurd
by Shangrila Height Realty LLP. Bavdhan Khurd, Pune 411021. View on Google Maps
- Launched
- 3 years 9 months promised
- Possession date (MahaRERA)
- 2 years 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 0%Early stageAverage across 2 buildings
- Units booked
- Bookings not reported
Project facts
| 3 BHK | 32 |
|---|---|
| 4 BHK | 3 |
| Other units (shops, offices or not given by type) | 9 |
| Total units | 44 |
| Buildings | 2 |
| Land | 0.8 acres |
| Complaints on MahaRERA (filed by or against the builder) | 1 |
Since Dec 2025: complaints 0 → 1
Compared with 6 similar projects in PIN 411021
Projects with 10–70 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 9 mths | 2 yrs 10 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | December 2028 | December 2027 |
| Concrete structure (RCC) complete | 0% | 38% |
| Complaints on MahaRERA (filed by or against the builder) | 1 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Infinia Vista | March 2025 | June 2027 | 70% | 13 of 30 booked (43%) |
| Livience Aleenta- MHADA | March 2025 | December 2028 | 9% | Bookings not reported |
| Shree Mangalam | February 2025 | March 2027 | 90% | 10 of 28 booked (36%) |
| Punyoday | February 2025 | June 2028 | 15% | 16 of 63 booked (25%) |
| KGS One | January 2025 | April 2027 | 60% | Bookings not reported |
| Polaris | May 2025 | December 2030 | 0% | Bookings not reported |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Shangrila Heights (MahaRERA P52100079619) is a residential project by Shangrila Height Realty LLP in Bavdhan Khurd, Pune 411021. It was launched in March 2025. It has 44 units in 2 buildings: 35 homes (3 & 4 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2028, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.
It has not reported any bookings to MahaRERA yet.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.