The Spectrum, Undri
by Shriram Properties Limited. Undri, Pune 411060. View on Google Maps
- Launched
- 10 years promised
- Possession date (MahaRERA)
- 8 years 6 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 0%Early stageAverage across 4 buildings
- Units booked
- 231 of 65735% booked
Project facts
| 2 BHK | 223 |
|---|---|
| 3 BHK | 363 |
| 4 BHK | 1 |
| Other units (shops, offices or not given by type) | 70 |
| Total units | 657 |
| Buildings | 4 |
| Land | 15.8 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 147 → 231
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 57% | 0% | 0% | 231 | |
| 1% | 0% | 0% | 147 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
The Spectrum (MahaRERA P52100080066) is a residential project by Shriram Properties Limited in Undri, Pune 411060. It was launched in April 2025. It has 657 units in 4 buildings: 587 homes (2, 3 & 4 BHK) and 70 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2035, unchanged since launch. Construction, averaged across its 4 buildings: excavation 57% complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.
231 of its 657 units are booked (35%). Since the December 2025 update, 84 more units have been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.