Skip to main content
← Back

Karthikeya Residency, Katraj

by Laxman Kala Constructions. Katraj, Pune 411046. View on Google Maps

Launched
4 years promised
Possession date (MahaRERA)
2 years 7 months awayPossession date unchanged since launch
Concrete structure (RCC)
50%Mid-constructionAverage across 2 buildings
Units booked
Bookings not reported

Project facts

2 BHK42
Total units42
Buildings2
Land0.6 acres
Landowner share13
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: structure 0% → 50%

Share on WhatsApp

Compared with 4 similar projects in PIN 411046

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 411046
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs2 yrs 6 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)May 2029December 2027
Concrete structure (RCC) complete50%19%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 5 months of the promised 4 years have passed
Concrete structure (RCC) 50% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2025Dec 2025Jul 2026Jun 2025: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 100%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 50%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 50%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%50%0%—
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Karthikeya Residency (MahaRERA P52100080171) is a residential project by Laxman Kala Constructions in Katraj, Pune 411046. It was launched in May 2025. It has 42 units in 2 buildings, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is May 2029, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) 50% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

It has not reported any bookings to MahaRERA yet. Since the December 2025 update, the reported concrete structure (RCC) has gone from 0% to 50%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100080171.Check it on MahaRERA (P52100080171)All projects in Ambegaon, Katraj