Chaandrai Galaxy, Ambegaon Budruk
by Sachin Developers. Ambegaon Budruk, Pune 411046. View on Google Maps
- Launched
- 3 years 11 months promised
- Possession date (MahaRERA)
- 2 years 6 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 0%Early stage
- Units booked
- Bookings not reported
Project facts
| 2 BHK | 10 |
|---|---|
| 3 BHK | 8 |
| Other units (shops, offices or not given by type) | 27 |
| Total units | 45 |
| Buildings | 1 |
| Land | 1 acre |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Compared with 5 similar projects in PIN 411046
Projects with up to 40 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 11 mths | 3 yrs 11 mths |
| Possession date extended | No | 0 of 5 |
| Possession date (MahaRERA) | April 2029 | December 2029 |
| Concrete structure (RCC) complete | 0% | 0% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Saideep Dwarka | May 2025 | December 2026 | 100% | Bookings not reported |
| Kohinoor A/C | March 2025 | February 2029 | 0% | Bookings not reported |
| Shree Ganesh Heritage | February 2026 | December 2030 | 0% | Bookings not reported |
| Amit Eternity | March 2026 | December 2029 | 0% | Bookings not reported |
| Shiv Harsh Vihar | April 2026 | December 2031 | 0% | Bookings not reported |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | — | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Chaandrai Galaxy (MahaRERA P52100080305) is a residential project by Sachin Developers in Ambegaon Budruk, Pune 411046. It was launched in May 2025. It has 45 units in 1 building: 18 homes (2 & 3 BHK) and 27 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.
It has not reported any bookings to MahaRERA yet.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.