Skip to main content
← Back

Nesterra - Phase 1, Lohegaon

by Triaa Skyscrapers LLP. Lohegaon, Pune 411047. View on Google Maps

Launched
5 years 6 months promised
Possession date (MahaRERA)
4 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
40%Mid-constructionAverage across 7 buildings
Units booked
177 of 52434% booked

Project facts

2 BHK239
3 BHK218
4 BHK44
Other units (shops, offices or not given by type)23
Total units524
Buildings7
Land12.5 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: structure 0% → 40%

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 4 months of the promised 5 years 6 months have passed
Concrete structure (RCC) 40% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2025Dec 2025Jul 2026Jun 2025: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 100%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 40%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 40%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%40%0%177
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Nesterra - Phase 1 (MahaRERA P52100080481) is a residential project by Triaa Skyscrapers LLP in Lohegaon, Pune 411047. It was launched in June 2025. It has 524 units in 7 buildings: 501 homes (2, 3 & 4 BHK) and 23 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2030, unchanged since launch. Construction, averaged across its 7 buildings: excavation complete, structure (RCC) 40% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

177 of its 524 units are booked (34%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 0% to 40%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100080481.Check it on MahaRERA (P52100080481)All projects in Lohegaon