Ved Krushnarang, Wadmukhwadi
by Krushnarang Mangalam Group. Wadmukhwadi, Pune 412105. View on Google Maps
- Launched
- 3 years 11 months promised
- Possession date (MahaRERA)
- 2 years 8 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 0%Early stageAverage across 3 buildings
- Units booked
- 56 of 27620% booked
Project facts
| 1 BHK | 25 |
|---|---|
| 2 BHK | 207 |
| 3 BHK | 33 |
| Other units (shops, offices or not given by type) | 11 |
| Total units | 276 |
| Buildings | 3 |
| Land | 1.8 acres |
| Landowner share | 36 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: total units 154 → 276
Compared with 6 similar projects in PIN 412105
Projects with 100–600 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 11 mths | 4 yrs 10 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | June 2029 | June 2030 |
| Concrete structure (RCC) complete | 0% | 22% |
| Share of units booked | 20% | 54% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| The Hallmark Wings D, E/F | July 2025 | December 2029 | 0% | 24 of 200 booked (12%) |
| Tanish Meridian | June 2025 | December 2030 | 57% | Bookings not reported |
| Clone Tiara PH-2 | August 2025 | October 2028 | 45% | 98 of 134 booked (73%) |
| Mangalam Midas City | September 2025 | December 2030 | 0% | 209 of 386 booked (54%) |
| K K Tathastu | May 2025 | December 2035 | 0% | 114 of 455 booked (25%) |
| Shreesha Icon | March 2025 | July 2029 | 92% | 88 of 154 booked (57%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 56 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Ved Krushnarang (MahaRERA P52100080801) is a residential project by Krushnarang Mangalam Group in Wadmukhwadi, Pune 412105. It was launched in July 2025. It has 276 units in 3 buildings: 265 homes (1, 2 & 3 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is June 2029, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.
56 of its 276 units are booked (20%).
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.