Dashabhuja Apartments, Parvati
by Profile Elegance LLP. Parvati, Pune 411009. View on Google Maps
- Launched
- 2 years 9 months promised
- Possession date (MahaRERA)
- 1 year 7 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 10%Mid-construction
- Units booked
- 1 of 128% booked
Project facts
| 3 BHK | 6 |
|---|---|
| 4 BHK | 6 |
| Total units | 12 |
| Buildings | 1 |
| Land | 0.1 acres |
| Rehab units | 6 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: structure 0% → 10%
Compared with 6 similar projects in PIN 411009
Projects with up to 30 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 2 yrs 9 mths | 2 yrs 9 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | May 2028 | July 2028 |
| Concrete structure (RCC) complete | 10% | 0% |
| Share of units booked | 8% | 30% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Peshwai | September 2025 | March 2027 | 100% | 3 of 10 booked (30%) |
| Manik Deepshree Cooperative Housing Society Limited | July 2025 | December 2028 | 0% | All 10 units booked |
| Shri Ramkrishna Paramhans Cooperative Housing Society | September 2025 | July 2028 | 0% | Bookings not reported |
| Smita Apartment | October 2025 | September 2029 | 0% | Bookings not reported |
| Uma | October 2025 | June 2028 | 0% | Bookings not reported |
| Manikdeep | June 2025 | October 2027 | 85% | 3 of 24 booked (13%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 10% | 0% | 1 | |
| 40% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Dashabhuja Apartments (MahaRERA P52100080942) is a residential project by Profile Elegance LLP in Parvati, Pune 411009. It was launched in August 2025. It has 12 units in 1 building, with 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is May 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 10% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
1 of its 12 units is booked (8%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 0% to 10%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.