Skip to main content
← Back

Grand Orion, Parvati

by Agastya Buildcon. Parvati, Pune 411009. View on Google Maps

Launched
3 years 4 months promised
Possession date (MahaRERA)
2 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stage
Units booked
4 of 2020% booked

Project facts

1 RK3
Other units (shops, offices or not given by type)17
Total units20
Buildings1
Land0.1 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 1 → 4 · total units 7 → 20

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 2 months of the promised 3 years 4 months have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Dec 2025: Excavation 0%Jul 2026: Excavation 50%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 50%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
50%0%0%4
0%0%0%1

"—" means MahaRERA shows no figure for that update.

About this project

Grand Orion (MahaRERA PC1260002500454) is a residential project by Agastya Buildcon in Parvati, Pune 411009. It was launched in August 2025. It has 20 units in 1 building: 3 homes (1 RK) and 17 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation 50% complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

4 of its 20 units are booked (20%). Since the December 2025 update, 3 more units have been booked.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration PC1260002500454.Check it on MahaRERA (PC1260002500454)All projects in Parvati