Skip to main content
← Back

Pandharinath Complex, Warje

by Shivsai Promoters LLP. Warje, Pune 411058. View on Google Maps

Launched
3 years promised
Possession date (MahaRERA)
2 years 3 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stage
Units booked
1 of 264% booked

Project facts

2 BHK19
Other units (shops, offices or not given by type)7
Total units26
Buildings1
Land0.3 acres
Landowner share14
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Compared with 4 similar projects in PIN 411058

Projects with up to 40 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 411058
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs3 yrs 8 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)January 2029August 2029
Concrete structure (RCC) complete0%0%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
9 months of the promised 3 years have passed
Concrete structure (RCC) 0% complete

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%1

"—" means MahaRERA shows no figure for that update.

About this project

Pandharinath Complex (MahaRERA PM1260002502071) is a residential project by Shivsai Promoters LLP in Warje, Pune 411058. It was launched in January 2026. It has 26 units in 1 building: 19 homes (2 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is January 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

1 of its 26 units is booked (4%).

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration PM1260002502071.Check it on MahaRERA (PM1260002502071)All projects in Warje