Millefiori, Wakad
by Futuristic Homes. Wakad, Pune 411057. View on Google Maps
- Launched
- 4 years 1 month promised
- Possession date (MahaRERA)
- 3 years 8 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 0%Early stage
- Units booked
- Bookings not reported
Project facts
| 3 BHK | 18 |
|---|---|
| Other units (shops, offices or not given by type) | 3 |
| Total units | 21 |
| Buildings | 1 |
| Land | 1.2 acres |
| Landowner share | 5 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Compared with 4 similar projects in PIN 411057
Projects with up to 40 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs 1 mth | 4 yrs 10 mths |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | June 2030 | October 2030 |
| Concrete structure (RCC) complete | 0% | 0% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Rajveer Garima Phase 2 | June 2026 | December 2031 | 0% | Bookings not reported |
| Siddhi's Sapphire Homes | January 2026 | December 2027 | 25% | Bookings not reported |
| Highness | January 2026 | December 2032 | 0% | 7 of 36 booked (19%) |
| Park Titan Phase V | June 2025 | August 2029 | 0% | Bookings not reported |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Millefiori (MahaRERA PM1260002600332) is a residential project by Futuristic Homes in Wakad, Pune 411057. It was launched in May 2026, which makes it one of the newest launches in Wakad, Hinjewadi, Marunji. It has 21 units in 1 building: 18 homes (3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is June 2030, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.
It has not reported any bookings to MahaRERA yet.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.