Niyam Vistta, Mundhwa

by Buildcraft Spaces · Mundhwa, Pune 411036 · Map

Launched
Jul 20262 yrs 5 mths originally promised
Possession (MahaRERA)
Apr 2029Extended by 4 mths
Concrete structure
20%Mid-construction
Booked
24 of 5345%
Price per sq ft
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
31
3 BHK
13
Other units
9
Total units
53
Buildings
1
Land
0.9 acres
Phases
1
MahaRERA complaints
0

Construction progress by tower

From the architect's Form 1 filed with MahaRERA. The last 4 updates per tower.

Last 4 updates
Building
UpdateStructureFinishes
Oct 202620%0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%20%0%24

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Construction cost spent

From the engineer's Form 2 filed with MahaRERA.

₹6.8 crore spent · latest estimate ₹34.1 crore · Oct 2026

Latest estimate ₹34.1 croreOct 2026: ₹6.8 crore6.8Oct 2026
₹ crore spent
Spent at each update
UpdateSpent
Oct 2026₹6.8 crore

Compared with 6 similar projects in PIN 411036

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411036
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 5 mths3 yrs 7 mths
Possession date extendedBy 4 mths2 of 6
Possession date (MahaRERA)Apr 2029Dec 2029
Concrete structure (RCC)20%0%
Units booked45%3%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Niyam Vistta by Buildcraft Spaces is a 53-unit project in Mundhwa, Pune 411036, launched in July 2026 with possession due in April 2029. 24 units booked out of total 53 units. The concrete structure (RCC) is 20% complete.

Read full summary

Niyam Vistta is a project by Buildcraft Spaces in Mundhwa, Pune 411036, registered with MahaRERA as PM1260002601280. It was launched in July 2026. It has 53 units in 1 building: 44 homes (2 and 3 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2029, extended by 4 months from the original December 2028. Construction: excavation complete, structure (RCC) 20% complete, final finishes not started.

24 units booked out of total 53 units (45%).