Kausar Parque, Kondhwa Budruk

by M/S Arham Construction · Kondhwa Budruk, Pune 411048 · Map

Launched
Sep 20266 yrs 3 mths promised
Possession (MahaRERA)
Dec 2032Not extended
Concrete structure
0%Early stage
Booked
18 of 15612%
Price per sq ft
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
45
3 BHK
56
Other units
55
Total units
156
Buildings
2
Land
2.3 acres
Phases
1
MahaRERA complaints
0
Reserved units
18

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%18

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 411048

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 411048
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs 3 mths4 yrs 4 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Dec 2032Dec 2030
Concrete structure (RCC)0%0%
Units booked12%0%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Kausar Parque by M/S Arham Construction is a 156-unit project in Kondhwa Budruk, Pune 411048, launched in September 2026 with possession due in December 2032. 18 units booked out of total 156 units. Work on the concrete structure (RCC) has not started.

Read full summary

Kausar Parque is a project by M/S Arham Construction in Kondhwa Budruk, Pune 411048, registered with MahaRERA as PM1260002602033. It was launched in September 2026. It has 156 units in 2 buildings: 101 homes (2 and 3 BHK) and 55 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2032, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.

18 units booked out of total 156 units (12%).