Skip to main content
← Back

Thorve House, Balewadi

by Vishva Developers. Balewadi, Pune 411045. View on Google Maps

Launched
1 year 9 months promised
Possession date (MahaRERA)
8 months awayPossession date unchanged since launch
Concrete structure (RCC)
17%Mid-constructionAverage across 3 buildings
Units booked
6 of 3119% booked

Project facts

2 BHK20
Other units (shops, offices or not given by type)11
Total units31
Buildings3
Land0.9 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: structure 0% → 17%

Share on WhatsApp

Compared with 6 similar projects in PIN 411045

Projects with 10–40 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411045
MeasureThis projectSimilar projects
Promised timeline (launch to possession)1 yr 9 mths2 yrs 7 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)June 2027November 2028
Concrete structure (RCC) complete17%56%
Share of units booked19%13%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 1 month of the promised 1 year 9 months have passed
Concrete structure (RCC) 17% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 17%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 17%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%17%0%6
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Thorve House (MahaRERA PR1260002500984) is a residential project by Vishva Developers in Balewadi, Pune 411045. It was launched in September 2025. It has 31 units in 3 buildings: 20 homes (2 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2027, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) 17% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

6 of its 31 units are booked (19%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 0% to 17%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration PR1260002500984.Check it on MahaRERA (PR1260002500984)All projects in Baner, Balewadi, Mahalunge