Infinity Spaces, Ravet
by Infinity Infracorp. Ravet, Pune 412101. View on Google Maps
- Launched
- 1 year 2 months promised
- Possession date (MahaRERA)
- 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 50%Mid-constructionAverage across 2 buildings
- Units booked
- 8 of 1942% booked
Project facts
| 1 BHK | 12 |
|---|---|
| 2 BHK | 6 |
| 3 BHK | 1 |
| Total units | 19 |
| Buildings | 2 |
| Land | 0.1 acres |
| Landowner share | 2 |
| Reserved units | 1 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: structure 35% → 50% · final finishes 0% → 25%
Compared with 6 similar projects in PIN 412101
Projects with up to 40 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 1 yr 2 mths | 2 yrs 7 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | December 2026 | May 2028 |
| Concrete structure (RCC) complete | 50% | 0% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Rose Paradise | October 2025 | July 2028 | 0% | Bookings not reported |
| Krishiv Elite | November 2025 | October 2027 | 0% | 17 of 24 booked (71%) |
| Nimbark Residency | September 2025 | May 2028 | 75% | Bookings not reported |
| Crestline Shreshth | November 2025 | December 2029 | 0% | Bookings not reported |
| Sukhakarta Residency | September 2025 | June 2027 | 0% | Bookings not reported |
| Shruti Ananta | December 2025 | June 2028 | 13% | 9 of 20 booked (45%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 50% | 25% | 8 | |
| 50% | 35% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Infinity Spaces (MahaRERA PR1260002501121) is a residential project by Infinity Infracorp in Ravet, Pune 412101. It was launched in October 2025. It has 19 units in 2 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) 50% complete, final finishes 25% complete. MahaRERA records do not show it as ready to move in.
8 of its 19 units are booked (42%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 35% to 50%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.